Kwinana, WA
Covalent Lithium Pty Ltd
Covalent Lithium Pty Ltd
15 months
Aug-21
Melchor were engaged by Covalent Lithium Pty Ltd to perform the Civil and Concrete package for the refinery, located in Kwinana, WA. This package includes bulk earthworks, drainage, road works, precast piling, underground services and concrete structure construction.
Melchor have installed over 2000 precast piles, 10km of underground piping, approximately 50km of underground LV/HV and communications cabling and earthing, and 25,000 cubic meters of concrete. Some of the piers in the processing plant are over 16m high and poured in one lift to maximise efficiency.
As part of the project the Melchor civils team worked with Western Power to construct the new switchyard associated with the project.
During 2022, Melchor achieved the following on the refinery site:
We provide services that include head contracts, sub-contracting and labour hire to project owners, EPC contractors and Tier-1 civil contractors.
Get in TouchUnlock a world of diverse opportunities with a company that invests in their team’s growth and wellbeing.
Join our TeamMelchor Perth
1/3 McDonald Street West
Osborne Park, WA 6017
(08) 6110 1988
admin@melchor.com.au
Melchor Karratha
Lot 2534 Coolawanyah Rd
Karratha, WA 6714
Melchor Bunbury
9 Marchant Street
Davenport, Bunbury WA 6230