West Musgrave Project
- Location: Musgrave Province of Western Australia
- Project Owner: BHP
- Year completed: 2023 - 2024
Located in the Musgrave Province of Western Australia, the West Musgrave Project involved the construction of a major copper and nickel mining operation.
Melchor was engaged to deliver all in-situ concrete works associated with the project, including excavation, backfilling, buried services, formwork, reinforcement and concrete placement.
The scope included the construction of a 28-metre-high primary crusher, two 50-metre-long reclaim tunnels, and two vertical roller mills, each requiring approximately 1,600 cubic metres of concrete. Melchor also completed the on-site precasting of tee-roff beams to support the project’s structural requirements.
Key highlights
44,000 bank cubic metres of excavation
33,000 compacted cubic metres of fill
8,000 linear metres of buried services
26,000 cubic metres of concrete required to complete the mining circuit
A single concrete pour of 1,060 cubic metres for a vertical roller mill foundation