South Flank - NPI works
- Location: Newman, Western Australia
- Project Owner: BHP
- Year completed: 2019 - 2020
Melchor was engaged to deliver the concrete package for two primary crushers on the South Flank project.
The concrete package for each crusher comprised approximately 1,900 cubic metres of concrete and involved complex formwork systems, including 12-metre-high walls and a 1.5-metre-thick suspended slab located 10 metres above foundation level.
Melchor was responsible for all permanent and temporary works, including the supply of labour, plant and materials.